Above water-level construction begins on Washington Bridge.
Among prominent achievements by RIDOT and CIRI members.
During the third and fourth quarters of FFY 2026, covering April through September of this year, RIDOT advanced numerous projects throughout the state. A few of the agency’s accomplishments, highlighted in its Q4 report released on October 30, include:

Drilling and installation of foundation shafts on the Washington Bridge Rebuild.
Washington Bridge Rebuild. On June 10, in-water construction was begun on this crucial project of extreme statewide importance. While continuing to build a construction platform along the Providence shoreline, crews began installing the first of 32 drilled foundation shafts, each extending approximately 130 feet to bedrock to support the new bridge’s piers and abutments.
Shaft installation and platform construction — conducted during daytime hours with noise, vibration and erosion controls — continued throughout July and August. By September 25, six foundation shafts had been installed and filled with concrete. The number had increased to ten by late October, as crews had also begun pouring concrete for foundation components above the shafts. Up-to-date information on the latest progress and developments is publicly available at www.washingtonbridgerebuild.com, the dedicated website for the project.

Rehabilitation operations on the I-95 15 Bridges project.
I-95 15 Bridges Project. A massive, multi-phase initiative in the metropolitan Providence area, this project is currently progressing across multiple active bridge sites in Bridge Group 04-R. RIDOT’s largest project ever, it is removing 15 bridges from the state’s backlog of poor-condition bridges along I-95 and Route 10 between Providence and Warwick.
The most consequential current work is the reconstruction of the Huntington Viaduct and the entire I-95/Route 10 interchange. A significant interchange demolition milestone was completed on the weekend of October 17 & 18, eliminating the immediate need for additional overnight I-95 closures. Other work underway includes:
· Bridge work at Broad Street, Jefferson Boulevard northbound and the Pawtuxet River
· Paving of I-95 South between the Pawtuxet River Bridge and Jefferson Boulevard
· Milling and paving Route 10 North within the project area
Click here to view a video montage of the 15 bridges comprising Bridge Group 04-R.

Missing Move demolition work at the I-95/Route 4 merge in East Greenwich.
Missing Move Project. This $144 million project spanning North Kingstown, East Greenwich and Warwick remains on track for overall completion in Fall 2027. The Route 4 North to I-95 South flyover bridge is still under construction. I-95 North is being connected to Route 4 South via a ground-level ramp. I-95 South traffic remains shifted to accommodate drainage improvements and construction of the bridge’s northern pier.
In late September, RIDOT also opened three new ramps providing better connectivity from Route 403 to the Quonset Business Park and the Route 1 (Post Road) business district. These ramps, which were not built when Route 403 was originally constructed 20 years ago, lead to:
· West Davisville Road to Route 403 East toward Route 1 and the main Quonset Point Business Park areas
· Route 403 West, coming from Route 1 toward Route 4, exiting onto West Davisville Road
· Route 1 (Post Road) to Route 403 West toward Route 4

Night bridge work on Route 37 in Cranston.
RIDOT also added a roundabout at the West Davisville Road/Compass Circle intersection, while making numerous safety improvements including new signage, striping and traffic signals. These new elements are designed to shorten travel times, make it easier for trucks and cars to get to/from destinations in the business park, and help reduce business park traffic on local roads.
Woonsocket Corridor Bridges. Scheduled for overall completion in the summer of 2028, this $22.7 million project is addressing five bridges and key road corridors across Woonsocket. Both the Diamond Hill Road Bridge over the Peters River and the Privilege Street Bridge reopened to traffic in September. Erosion protection was completed at the Mill Street Bridge, along with ongoing repairs to its arch. The Wood Avenue Bridge is closed for repairs and ongoing demolition.